  • 潔淨室驗收確認的方法
    來源:http://www.relexus.com 瀏覽: 發布日期:2020-12-23
    潔淨室潔淨度的確認,有三種方式,分別為空態驗收、靜態驗收和動態驗收。空態驗收指潔淨室設施已經建成,但尚未安裝生產設備,無材料及人員流動。靜態驗收設施已經建成,生產設備已經安裝,並開始運行,但無生產人員。設施已按規定的狀態運行,有規定的人員子在場。
    There are three ways to confirm the cleanliness of clean room, which are empty acceptance, static acceptance and dynamic acceptance. Empty acceptance refers to that the clean room facilities have been completed, but the production equipment has not been installed, and there is no flow of materials and personnel. The static acceptance facilities have been built, and the production equipment has been installed and put into operation, but there are no production personnel. The facility has been operated in accordance with the specified conditions and there are specified personnel present.
    三種驗收方式是層層遞進的,隻有上一層驗收通過之後,才能進行下一層的測試。然而,僅僅做基礎的驗收是不規範也不準確的。
    After that, there is only a three-level acceptance test. However, it is not standard and accurate to only do the acceptance of the foundation.
    潔淨室竣工驗收應在對各分部工程做外觀檢查、單機試運轉、係統聯合實運轉,空態或靜態條件下的潔淨室性能檢測和調整以及對有關的施工檢車記錄審核合格後進行。
    The completion acceptance of clean room shall be carried out after the appearance inspection, single machine test run, system joint actual operation, clean room performance test and adjustment under empty or static conditions, and relevant construction vehicle inspection records.
    各種管道、自動滅火裝置及淨化空調設備,空調器、風機、淨化空調機組、空氣過濾器和空氣吹淋室等的安裝應正確、牢固、嚴密。高中效過濾器與風管連接及風管與設備的連接處應有可靠密封。各類調節裝置應嚴密、調節靈活、操作方便。淨化空調器、靜壓箱、風管係統及送、回風口無灰塵。潔淨室的內牆麵、吊頂表麵和地麵,應光滑、平整、色澤均勻,不起灰塵,地板無靜電現象。
    All kinds of pipes, automatic fire extinguishing devices and purification air conditioning equipment, air conditioners, fans, purification air conditioning units, high efficiency air filters and air shower rooms shall be installed correctly, firmly and tightly. The connection between high and medium efficiency filter and air duct and between air duct and equipment shall be reliably sealed. All kinds of regulating devices should be tight, flexible and easy to operate. Clean air conditioner, static pressure box, air duct system and air supply and return outlets without dust. The interior wall, ceiling surface and floor of the clean room should be smooth, flat, uniform in color, free from dust, and the floor should be free of static electricity.
    無菌室裝修
    潔淨室內各類配電盤、櫃和進入潔淨室的電氣管線管口應可靠密封。單機運轉合格後,必須進行帶冷(熱)源的係統正常聯合試運轉,並不少於8h。係統中各項設備部件聯動運轉必須協調,動作正確,無異常現象。
    All kinds of distribution boards and cabinets in the clean room and the electrical pipeline orifices entering the clean room shall be reliably sealed. After the single machine operation is qualified, the normal combined test run of the system with cold (heat) source must be carried out, which shall not be less than 8h. The linkage operation of various equipment components in the system must be coordinated, the action must be correct, and there is no abnormal phenomenon.
    潔淨室使用驗收後,應編寫使用驗收報告,其主要內容有:
    After the use acceptance of clean room, the use acceptance report should be prepared, which mainly includes:
    1、潔淨室中各種設施(包括生產工藝設備)等的開啟狀態描述;
    1. Description of opening status of various facilities (including production process equipment) in clean room;
    2、測試的潔淨室(區)人員及其活動情況的描述;
    2. Description of the clean room (area) personnel tested and their activities;
    3、分項測試記錄及分析意見(包括測試點位置、座標等);
    3. Itemized test records and analysis opinions (including test point locations, coordinates, etc.);
    4、測試儀器的有效校驗證書;
    4. Valid calibration certificate of test instrument;
    5、潔淨室的驗收出具相關結論。
    5. Relevant conclusions should be issued for the acceptance of clean room.