    一、施工的資質要求
    1、 Qualification requirements for construction
    雖然實驗室裝修具有其特殊性,但是目前實驗室施工還是依照建築行業的資質證書規定來明確施工規定!
    Although the laboratory decoration has its particularity, but the current laboratory construction is still in accordance with the construction industry qualification certificate provisions to clear the construction provisions!
    那麽實驗室施工都包含哪些方麵的問題呢?一般的實驗室施工包括了機電工程安裝、建築裝修、環境保護、消防安全、氣路等!因此 在資質證書這方麵,一般必須機電工程安裝資質證書、裝飾設計裝修資質、資質、消防資質、二類壓力容器施工資質證書、智能化資質等,假如做施工總承包新項目得話,就必須施工總承包的各種資質證書。
    So what are the problems in laboratory construction? The general mechanical and electrical engineering, environmental protection and installation of the laboratory are included! Therefore, in terms of qualification certificate, it is generally necessary to have electromechanical engineering installation qualification certificate, decoration design and decoration qualification, environmental protection qualification, fire protection qualification, class II pressure vessel construction qualification certificate, intelligent qualification, etc. If a new construction general contracting project is obtained, all kinds of qualification certificates of construction general contracting must be obtained.
    二、施工的具體內容
    2、 Specific contents of construction
    實驗室裝修主要針對房間內一部分,一般包含了裝飾設計、給水排水、暖通工程、電氣設備、智能化係統、氣路、汙水、有機廢氣處理、實驗室家具等。
    Laboratory decoration is mainly for a part of the room, which generally includes decoration design, water supply and drainage, HVAC engineering, electrical equipment, intelligent system, gas path, sewage, organic waste gas treatment, laboratory furniture, etc.
    裝飾設計則包含了路麵的地麵找平跟環氧地坪的施工、隔斷牆的施工、裝修吊頂的施工、窗門的施工、窗簾布的施工、設備基礎的施工等;
    The decoration design includes the ground leveling and epoxy floor construction, partition wall construction, ceiling decoration construction, window and door construction, curtain cloth construction, equipment foundation construction, etc;
    給水排水包括了給排水、排水管道、純淨水等;
    Water supply and drainage includes water supply and drainage, drainage pipeline, purified water, etc;
    暖通工程包括了通風風管、空調管路、清潔管路、空調水管路、機器設備的安裝、空調風管安裝等;
    HVAC engineering includes ventilation duct, central air conditioning pipeline, cleaning pipeline, air conditioning water pipeline, installation of machine equipment, air conditioning duct installation, etc;
    電氣設備包括電纜電線施工、照明燈具電源插座的施工、配電櫃的施工等;
    Electrical equipment includes cable and wire construction, lighting lamp power socket construction, power distribution cabinet construction, etc;
    智能化係統包括的內容依據智能化係統所包含的係統,一般包含磁感應電子器件、走線、服務器及主機房的施工;
    實驗室裝修
    The contents of intelligent system include the construction of magnetic induction electronic devices, wiring, server and host room according to the system included in the intelligent system;
    氣路主要是各種氣體管道、氣罐間及閘閥的安裝;
    The gas path is mainly the installation of various gas pipelines, gas tanks and gate valves;
    汙水主要是汙水站房、汙水機器設備的施工;
    Sewage mainly includes the construction of sewage station building and sewage machinery and equipment;
    實驗室家具包含了各種實驗室的家具,試驗台、實驗櫃、通風降溫設備、給排水設備、氣路類機器設備、安全性層麵的機器設備這些。
    Laboratory furniture includes a variety of laboratory furniture, test bench, laboratory cabinet, ventilation and cooling equipment, water supply and drainage equipment, gas path machinery and equipment, and safety level machinery and equipment.
    三、施工步驟
    3、 Construction steps
    全部新項目的施工步驟實際上跟別的機電工程安裝的施工步驟差別並並不是非常大,自身從係統上,也就是機電工程管路的安裝、機器設備的安裝及其裝飾設計的安裝,總體的施工便是這三一部分的有機結合,非常是機電工程管路跟裝飾設計安裝的融合,不一樣的裝飾設計作法會規定不一樣的施工步驟。
    In fact, the construction steps of all new projects are not very different from those of other mechanical and electrical engineering installation. From the system, that is, the installation of mechanical and electrical engineering pipeline, the installation of machinery and equipment and the installation of decoration design, the overall construction is the organic combination of these three parts, which is very different from the integration of mechanical and electrical engineering pipeline and decoration design and installation Decoration design method will stipulate different construction steps.
    基本的步驟是先做路麵的地麵找平,同歩能夠做機電工程主管的安裝,這兩個流程前後左右施工都能夠,僅僅地坪找平時,工作人員在施工地區無法施工,因此 還是看時間及方案的分配,此環節各種大中型機器設備的購置都能夠順利進行。
    The basic step is to level the road surface first, and then to install the electrical and mechanical engineering supervisor. The construction can be carried out before and after the two processes. Only when the floor leveling is carried out, the staff can not carry out construction in the construction area. Therefore, it depends on the allocations of time and scheme, and the purchase of various large and medium-sized machinery and equipment can be carried out smoothly.
    許多管路穿隔斷牆必須搞好預埋孔,針對一些不上頂的隔斷牆能夠先做,中後期在裝修吊頂上再做管路都能夠,但是務必裝修吊頂內室內空間充足,要不然就無法施工。
    Many pipelines through the partition wall must do a good job in the embedded hole, for some of the partition wall can be done first, in the middle and later period in the decoration of the ceiling pipe can be done, but must be decorated ceiling interior space is sufficient, otherwise it can not be constructed.
    一部分規定潔淨度等級較為高的管路更好是等房間內各種塵土大的施工搞好再做,防止環境汙染,或是提早搞好防護措施。
    Some of the pipelines with higher cleanliness level are better to wait for the construction with heavy dust in the room to prevent environmental pollution, or take protective measures in advance.
    進行主管與隔斷牆的施工後,基礎就可以依照立管及裝修吊頂,這時關鍵機器設備也基礎能夠交貨,同歩能夠做機器設備的安裝,及其在裝修吊頂內機器設備的起吊,這正中間會存有比較多必須融洽的地區,終究裝修吊頂內室內空間比較有限,各種立管假如提早沒有排好,或是做了BIM的撞擊查驗得話,非常容易造成各種交叉式的難題,因此 這時更好是每日都匯報工作融洽,溝通交流,降低難題的出現和返修。
    After the construction of the main pipe and partition wall, the foundation can be in accordance with the riser and decoration ceiling. At this time, the key machinery and equipment can also be delivered. At the same time, the installation of machinery and equipment and the lifting of machinery and equipment in the decorated ceiling can be done. There will be more areas in the middle that must be harmonious. After all, the interior space in the decorated ceiling is relatively limited. If all kinds of risers are not available in advance If there is a good arrangement or BIM impact inspection, it is very easy to cause a variety of cross type problems. Therefore, it is better to report the work daily, communicate harmoniously, and reduce the occurrence and repair of problems.